Tasks - Schedule 1.0

The current schedule for the 1.0 release, which should be ready by the time that Xfld 0.3/1.0 is released (depends on Xfce 4.4.0 progress).

10/2004 - 03/2005

Research in the area of file managers; try to figure out the problems of other file managers, so that we don’t repeat them.

Decide on the basic user interface (prototype required?).

Finish the overall design, and write some sample code to do performance measuring on the critical parts (MIME-detection and the like).

04/2005 - 07/2005

Implement the code, adjusting the design on-the-fly if necessary.

Experiment with the user interface.

End of July 2005

Final check on the user interface.

Beginning of August 2005

User interface/string freeze. Translation and user documentation process starts now.

Beta stage, write test cases for the code. Bugfixing/stabilizing the code.

End of August 2005

Release candidates. Final fixes.

Documentation/translation freeze.

Beginning of September 2005

Release version 1.0.0, together with Xfld 0.3/1.0.

 